East Boston - Chelsea
Creek Action Group
Meeting Minutes --
December 11, 2002
MEETING MINUTES – December 11, 2002
Attending: Vinny Ieni, Leigh Hall, Lucy
Del Muto, Ana Maria Gomez, Nancei Radicchi, Sal Matti, Antonio Gambale,
Roberta Horn, Arthur Horn, Robertson Ward, Grace Zuccaro, Stanley Buonagurio,
Aldo Oirano, Patricia Fidler, Florence D’Avella, Edith DeAngelis, Susan
Voloshian, Christopher Blackler, Anjie Preston, Paul Sutton and Lucas Murray
(Boston Parks), Sarah Kelley (Boston Harbor Association), and Morgan Wilson
and Stacey Chacker (NOAH).
-
Meeting Minutes: November 13th
meeting minutes were accepted.
Updates/News/Misc:
-
CCAG Holiday Party (w/ Chelsea) – Mon.
12/16 at 7:00 at Isabelle’s Café in Chelsea.
-
Chelsea Creek Vision Plan: Stacey,
Aaron, and Roseann are commenting on the 1st draft report.
Anyone is welcome to review the next draft (when it has been cleaned up).
-
We held a Comparative Risk Assessment (CRA)
Resident’s meeting in Chelsea in November. Pat, Leigh and Nancei were
there from E.B. with Chelsea residents. Came up with a good list of
recommendations to the Environmental Protection Agency (EPA) to follow up
on the CRA. We will share these at another meeting. The main
recommendation is to have EPA form a multi-agency and inter-agency group
to coordinate and share data and other information regarding air and water
quality in the Chelsea Creek area. We are in the process of setting up a
meeting with the EPA Regional Administrator, Bob Varney, and will have
representatives from the CRA Residents Committee attend that meeting.
-
EPA asked CCAG and Urban Ecology
Institute (UEI) staff to participate in a meeting with the EPA Regional
Administrator and Linda Fisher (Asst Director in D.C.) to share
information how EPA Region 1 works with groups they are providing grants
to. Many groups were there. Afterwards, they asked CCAG and UEI to take
EPA staffers on a tour of Chelsea Creek. This was a last minute request.
We will follow-up w/ letters to Mr. Varney and Ms. Fisher. It was a good
opportunity to highlight the problems and opportunities around Creek, as
well as all of the good community work.
-
Stacey explained that CCAG is in the
process of formalizing a partnership with UEI in order to do fundraising
and publicity together. EB-CCAG endorsed this idea wholeheartedly.
-
Barges with Styrofoam on the Creek:
Tony and Brian from the Boston Harbor Association followed up with each
other. Brian contacted Coastal Zone Management who sent us a "Derelict
Vessel" report to be submitted to Dept. of Environmental Management.
Stacey and Tony will fill out if needed. EB Sun-Transcript writer called
Stacey to inform CCAG that Attorney General Riley and the Dept. of
Environmental Protection filed lawsuits against Walton Systems and Chasen
(owner of the barges w/ Styrofoam) for polluting the Chelsea River, and to
get a quote from CCAG. Stacey gave a quote and told him to call Tony for
another quote. Aaron will follow up with the Attorney General’s office for
more information. Jay Ash, Chelsea City Manager, said that the lawsuits
are partly due to pressure from the community (aka, CCAG!).
-
Boston Greenspace Alliance is holding a
public forum focusing on the importance of Parks and Greenspace on Sat.
Feb. 1st from 8:30 to 2 p.m. at the Great Hall, Codman Square
Health Center in Dorchester. Nancei and Ana Maria would be interested, and
suggested that B. Amore may also be interested.
-
Charles/Felton Neighborhood Assn
requested CCAG members to attend a potluck to provide info on what we do
in Waltham. Nancei and Susan volunteered. Susan will contact them.
-
Condor Street Urban Wild If anyone has
questions, call Luke at 635-4505.
Luke Murray from Parks Dept. provided the
following update and information:
-
He got a call from to inform him that
the silt boom (a barrier in the water) was letting silt get out of the
Urban Wild into the Creek. Luke looked into it and believes that it was
just due to the installation of the salt marsh, but will keep an eye on
it. What he did notice is that the boom is keeping garbage from the Creek
from getting into the Urban Wild!
-
The project is on budget (which is
great!).
-
Contractors will probably stop before
the New Year, and start up again in early spring – depending on the
weather. The new completion expected completion date is June 2003. He
checks up on contractor 2-3 times/week. Basically contractor they are
moving the soil into the mound. Doing a lot of preventative work for
erosion control. They are using jute mesh on top of the soil, and using
crushed concrete as a sub-material to help stabilize the soil. They’ve
also started driving piles for the pier – however, were unable to go to
the required depth. They are now dealing with a structural engineer to see
if the piles are steady enough as they cannot go deeper. They will begin
to build the pier, but as they cannot put the railings on until the
seawall is in (spring), they will put up a gate to keep people off the
pier.
-
Water system: there was adequate funds
to put in the water system, so he made a critical decision to install the
system as it needs to be done before earth moving is completed. It will
allow for manual irrigation – with 12 quick cuppler valves interspersed
throughout the site. Don’t need to be drained in the winter. Basically,
it’s a brass fitting that can accommodate a garden hose or an impact
sprinkler.
-
The current hill is not in its final
shape. This hill contains the majority of contaminated materials from the
site, and will be capped with plastic and then 3 feet of clean soil. There
was more contaminated soil on site than Parks anticipated, thus they need
to spread an additional 6 inches of contaminated soil throughout the whole
site (the cost to haul it off site would be exorbitant).
-
50% of the salt marsh is planted (the
rest will be done in the spring) in a clay silt material that holds it in,
but doesn’t impact root development. Great Meadows from Riley is doing the
salt marsh. Parks is holding back 60% of their contract fee during the
3-year maintenance/warranty period that Great Meadows provides. This
maintenance period is from Spring 2003 to Spring 2006.
-
Contractor got the Boston Water and
Sewer Commission drain line in, with a new pipe and catch basin. This has
helped to reduce/eliminate flooding on Condor Street in heavy rains.
-
Material for walkways: Originally the
walkways were to be bluestone dust. However, he proposed concrete with
aggregate (stones that can be in different colors) for the following
reasons: 1) Boston Sand and Gravel (who used to own this site) gave
$50,000 in cash and $25,000 in donated materials (specifically "flowable
fill", or concrete); 2) He has had negative experiences using bluestone
dust at other sites; big maintenance issue – weeds grow throughout, it
pushes up borders. B. Amore told him that she prefers concrete (but would
like to pick out the color stones for the area with their piece). He says
it’s a more durable product, and although is a little bumpy, is still
wheelchair accessible.
-
Aiming for April to get the public art
installed. May not include second piece (the bronze boat).
-
Cobblestones: Contractor would like to
use these for curbing (on borders of walkways) instead of concrete. This
would save $6000, and in long term would be more durable. All agreed that
this would be a good re-use of the cobblestones.
-
B. would like to do something with the
old boat pieces and bollards on site. She would also like to drape the old
chain on site over the where the N-Star channel marker is (N-Star has an
utility easement on site). He will talk to B. about this, and it having
contractors put aside.
Participants posed questions regarding
the following issues – responses follow:
-
Fire Truck access to the pier –
doubtful a truck could get there, though fireboats would have easy access.
Since pier is so small, if there were a fire, it would probably burn
before any fire truck/boat could get there.
-
Trash pick-up: There are several
trashcans on the site. Parks will pick up regularly.
-
Maintenance: As part of supplemental
environmental project (SEP), Parks Dept has a dedicated fund of
$10,000/year for 15 years for maintenance. Parks can sub-contract with a
private landscaper to do this job. Paul Sutton, the new Urban Wilds
Coordinator will be responsible for coordinating this.
-
Fencing: discussed whether site should
have fencing in front of the site (currently not enough resources for a
whole fence (unless it was chain-link, which no one wants). Luke explained
that there is a big incline right at the sidewalk, and suggested that may
not need fencing across the whole site, but that it would be nice to
accentuate the entrances. Tony suggested putting bollards and chain.
-
Lighting: Question regarding adequate
lighting. Nancei pointed out that we’ve discussed this issue and decided
that as it is a "wild" site, it would be best to leave no internal parks
lights as that impacts plant and wildlife ability to live there (they need
darkness too). However, it was pointed out that lights are needed on the
street. Luke said to talk to Joe Banks at the DPW Street Lighting
Division.
-
Graffiti on public art: It was
suggested that the rocks be sprayed with an anti-graffiti product. This
will not be done as B and Woody said this would discolor the stones. Luke
said that Parks has a power wash system to remove graffiti.
Stacey reminded all that NOAH will be hiring a Program
Coordinator to 1) coordinate environmental youth program; 2) do organizing
around the Urban Wild – with a Friends Group (or EB-CCAG sub-committee) that
could act as a crime watch and/or develop special recreational/cultural
programs at the site (e.g. Catch and Release Fishing programs, nature walks,
concerts, etc); and 3) work with Chelsea to co-coordinate a couple
cross-Creek events (such as past boat tours). This position will be
partially funded with $12,500/year of SEP funds (that EB-CCAG endorsed at a
past meeting).
We will make a decision re: walkway material at Jan. 15th
meeting. Luke will bring in pictures of concrete paths with crushed
aggregate and Leigh will take pictures of an example of this material in
front of the Museum of Science. Luke will go to Boston Sand and Gravel to
look at their aggregate, and will look into the possibility of doing
chemical staining to the concrete.
Boudreau Boatyard
-
Leigh reported that we held a press
conference on 12/3 with about 12 people in freezing weather (Anna Lane who
spoke was quite the trooper!). The EB Sun-Transcript, Globe and
Neighborhood Network News covered the event. Stacey reported that the ISD
Commissioner called at 11:05 to see where the conference was (due to
freezing weather, it was over! but was a positive sign that he showed up).
Stacey sent copies of the new articles to the Board of Appeals and all of
the politicians.
-
Vinny reported that the date for the
Board of Appeals Hearing, scheduled for 12/17 has been changed. No new
date is set yet. Leigh, Lucy, Bobby and Stacey will attend (if they are
available).
Belle Steele
-
Vinny reported on the Boston
Redevelopment Authority (BRA) Public Hearing held on 12/9. Vinny, Bobby,
Arthur and Gail attended. Consultants stated that they did not owe EB
anything for developing a self-storage unit. Development will provide 2
full-time and 4 part-time jobs.
-
We reviewed the draft comment letter
from CCAG to the BRA (as part of the Article 80 Review process). Stacey
will incorporate comments and mail in before the 12/23 deadline. In the
draft, one of our requests is that they pay for a design plan for a
pedestrian/bike pathway on the rail trail.
EB-CCAG Year-in –Review and/or Propose one-liners for
Chelsea Creek Restoration Project. As anticipated, we did not have time
for these items, so will put on January agenda.
NOAH proposed Housing on Corner of
Border/Condor Streets
Morgan Wilson, NOAH Real Estate Project
Manager came to the meeting to discuss a proposed development project at
this corner and get feedback. He showed three different site plans and
explained each one. He also provided the following information, some in
response to comments below:
-
Each plan has a further "set back" than
other housing in the area (that means that the house is set back further
from the sidewalk (and in this case has shrubbery in the front). The plans
are trying to fit in with the rest of the neighborhood in terms of
character of housing.
-
For affordable units, required to have
.7 spots/unit (or 11 spots for 16 units).
-
The primary concern that he has heard
in previous meetings is the need for additional parking. NOAH is talking
to Shore Plaza (which is across the street) about long-term leasing of
many spots (only about ½ are used on a regular basis).
-
In order to purchase any NOAH
homes/condos - people need to apply and qualify to enter the lottery.
Purchasers must be below 80% of median income. Federal law requires that
NOAH advertise in several languages and outside of the immediate
neighborhood. NOAH advertises in the Spanish papers (which are regional -
thus the common complaint that NOAH is advertising in Lawrence).
-
NOAH is proposing 15-16 units ((condos)
for homeownership) in order to keep units affordable. The problem is that
building and land acquisition costs have gone up and money sources have
decreased. So in order to be able to financially complete a project, need
to develop enough units to have it help pay for itself. Estimates that
units will cost about $140,000-$160,000.
-
NOAH agrees that we need to preserve
open space. We are trying to incorporate into the site plan with more
greenery in front of each building and trees and shrubs in the parking
areas. In addition, NOAH is working with committees such as EB-CCAG to get
more open space. However, there is also a housing crisis. Also, it is
beneficial to introduce homeownership in an area with so much rental
housing to help improve it.
-
Some of the buildings four floors.
However, this would not cause shade effect on neighboring houses as the
new housing would be at the bottom of a reasonably steep slope, and thus
would not tower of neighboring houses.
-
NOAH purchased this piece of property
for $405,000.
Comments:
* there are many social service type
programs in the immediate vicinity - Trinity, Meridian House and others,
as well as Shore Plaza East, making the overall area too dense; * Border
St is a dangerous area for driving (many speeding cars and accidents)
and pedestrian crossing. Believes that NOAH has an obligation to de-densify
(put 3 buildings w/ three units) - in order to address concerns -
height, density, traffic, egress onto Border St from parking lot,
overpopulation, lack of open space. Emphasized the importance of
overlook over the water - it is the confluence of the Chelsea and Mystic
Rivers as well as Boston Harbor, site of sinking of the Diana (across
the way).
-
Nancei recommended equal parking spots
and housing units. Don’t depend on Shore Plaza or street for parking. She
believes that every adult living there will have a car - which could be up
to 32 cars.
-
Susan pointed out that City workers are
required to live within Boston, and that many do not make enough to do so
- thus need for affordable housing. However, expressed concern about
housing low-income people all together. Also expressed problem of
slumlords charging too much rent.
-
Vinny discussed the 40B rule that
states that each town needs to have a certain percentage of affordable
housing. Many agreed that there should be more affordable housing in the
suburbs.
-
Bobby expressed concern regarding 4
story buildings stealing sunshine from neighboring housing due to shade
impacts.
-
Others expressed concerns re: density
and parking, and shade on other units. However, as it was late, we did not
have time to take comments from everyone.
EB-CCAG 2003 meeting schedule
All meetings, unless otherwise indicated
will be at 6:30 p.m. at the Harborside.
In case of snow (and the Harborside is
closed) our meeting will be held the following Wednesday.
January 15th February 12th
March 12th April 9th May 14th June 11th
July 9th August 13th September 10th October
8th
November 12th December 10th
Minutes submitted by Stacey Chacker. Call 617-569-0059
ext. 13 with corrections or additions.
Source of meeting minutes: Stacey.Chacker@noahcdc.org Contact her for
more information.
|